Questions that use this term
Process·Finance
A project's earned value analysis shows a Cost Performance Index (CPI) of 0.85 and a Schedule Performance Index (SPI) of 1.05. The sponsor asks the project manager to explain the current health of the project.
How should the project manager characterize project performance?