Questions that use this term
Process·Governance
Midway through execution, a customer requests an enhancement that was not part of the original scope but would significantly improve the product's usability. The project manager believes it is a good idea and has spare budget contingency.
What should the project manager do?
Business Environment·Governance
A project manager is nearing project closure when a stakeholder requests a scope addition that would provide significant business value but was not in the original charter. Funding for the addition is available in the sponsor's discretionary budget.
What should the project manager do?