People·Stakeholders·ECO 1.8 — Negotiate project agreements
During negotiation for additional resources, a functional manager refuses to release a specialist needed for a critical project task, citing competing departmental priorities. The project schedule will slip without this resource.
What should the project manager do FIRST?