Scope Baseline

The approved version of the scope statement, WBS, and WBS dictionary, used as a basis for comparison.

Original SimCert study summary; not an official PMI® glossary definition.

Performance domain · SchedulePrinciple · Adopt a Holistic ViewExam domain · Process

Questions that use this term

Process·Schedule

A project manager discovers that the work breakdown structure (WBS) does not include a deliverable that stakeholders assumed was in scope. The project is already in the execution phase, and the team has limited capacity.

What should the project manager do FIRST?